OVERVIEW

After a review of Council assets, it was determined that several of them were in poor condition and in need of urgent repair.

Council made a commitment to residents to embark on an asset improvement project, including:

  • Renewing Roads and Footpaths
  • Improving Community Facilities
  • Pruning our Street Trees
  • Making our Town Centre Attractive
  • Improving Green Spaces
  • Making our Streetscapes Look Clean and Tidy

Since July 2023, Council has been working hard to fulfill this commitment. To date*, Council has spent $2.5 million on footpath upgrades, $906,000 on road resurfacing and $45,000 on kerb and gutter works. We’re well on track to deliver 117 footpath, 38 road and 33 kerb and gutter upgrades by June 2024.

Below you will find examples of Your Rates at Work.

* As at 12 April 2024.


ROADS AND FOOTPATHS

Council has undertaken a significant project to upgrade and repair our roads and footpaths. This will be an ongoing project for the next couple of years. Below you can see examples of the work, and a list of roads and footpaths completed so far.

Francis Street, Strathfield

Francis Street, Strathfield Before

From Shortland Ave to Hyderbrae St

Finish Date: 22 February 2024

Drew Street, Strathfield

Drew Street, Strathfield

From Matthews St to Webber St

Finish Date: 14 December 2023

Vernon Street, Strathfield

Vernon Street, Strathfield

From Brunswick Ave to Alviston St

Finish Date: 4 December 2023

Hope Street, Strathfield South

Hope Street, Strathfield

From Madeline St to Cosgrove Rd

Finish Date: 20 December 2023

Arthur St - From Francis St to Fraser St 4/12/2023
Vernon St - From Brunswick Ave to Alviston St 4/12/2023
Vernon St - From Carrington Ave to Brunswick Ave 4/12/2023
Dean St - From Barton St to Brooklyn St 5/12/2023
Dean St - From Brooklyn St to Dunlop St 5/12/2023
Dean St - From Frances Ave to Manning Ave 5/12/2023
Dean St - From Homebush Rd to Barton St 5/12/2023
Dean St - From Manning Ave to Holmwood Ave 5/12/2023
The Crescent - From the end to Richmond Rd 7/12/2023
Drew St - From Matthews St to Webber St 14/12/2023
Ford St - From Roberts Rd to Wentworth Rd
Wallis Ave - From Ada Ave to Strathlora St
14/12/2023
Wallis Ave - From High St to Liverpool Rd
16/12/2023
Verona St - From Rickard Rd to Wallis Ave
16/12/2023
Mintaro Ave - From Macarthur Ave to Amaroo Ave
18/12/2023
Oxford Rd - From Todman Pl to Barker Rd
19/12/2023
River St - From Mcencroe St to the end
19/12/2023
Hope St - From Madeline St to Cosgrove Rd
19/12/2023
Cutbush Ave - From Chisholm St to the end
20/12/2023
Davidson St - From Liverpool Rd to Marlene Cres
24/12/2023
Davidson St - From Marlene Cres to the end
24/12/2023
Homebush Rd - From Mintaro Ave to Long St
24/12/2023
Ford St - From Roberts Rd to Wentworth Rd
24/12/2023
Wakeford Rd - From Kingsland Rd to Cotswold Rd
10/01/2024
High St - From Cross St to Eve St
11/01/2024
Wallis Ave - From Verona St to High St
15/01/2024
Madeline St - From Cleveland St to Pilcher St
21/01/2024
Pilcher St - From Madeline St to Cosgrove Rd
29/01/2024
Hampstead Rd - From Exeter Rd to Kessell Ave
29/01/2024
Hampstead Rd - From Tavistock Rd to Arthur St
5/02/2024
Howard St - From Myall Cres to The Close
5/02/2024
Pemberton St - From Newton Rd to the end
9/02/2024
Shortland Ave - Howard St to Pemberton St
9/02/2024
Mcencroe St - From Anselm St to River St
9/02/2024
Mintaro Ave - From Homebush Rd to Noble Ave
13/02/2024
Wallis Ave - From Glenarvon St to Augusta St
13/02/2024
Homebush Rd - From The Crescent to Burlington Rd24/12/2024

Punchbowl Rd- From Robinson St to Patricia St, Greenacre

June 2024

Chisholm St - From Chatfield Ave to Cutbush Ave

June 2024

Cleveland St - From Madeline St to Cosgrove Rd

June 2024

Amaroo Ave - From Noble Ave to Liverpool Rd

June 2024

Beresford Rd - From Homebush Rd to Broughton Rd

June 2024

Brooklyn St- From Liverpool Rd to Dean St

June 2024

Carrington Ave- From Nichol Pde to Vernon St

June 2024

Wentworth Street, Greenacre - Norfolk Rd to Ford St 16/12/2023
Howard Street, Strathfield - Karuah St to Barker Rd 22/01/2024
Francis Street, Strathfield - Shortland Av to Hyderbrae St 22/01/2024

Dean St, Strathfield South (Hillcrest Av to Everitt Pl)

April 2024

Dean St, Strathfield South ( Everitt Pl to Edward St/Maria St)

April 2024

Dickson St, Strathfield

April 2024

Ilandilo Ave, Strathfield

April 2024

Highfield Crescent, Strathfield (High St to the end).

June 2024

Coronation Pde, Strathfield South (Plymouth St to Hill St)

June 2024

Bede St, Strathfield South (Anslem St to St Annes sq)

June 2024

Bede St, Liverpool Road to Anslem St.

June 2024


LED LIGHT UPGRADE

Council is working with Ausgrid to replace existing street lights with energy efficient LED lights.

For the next 2 years, 1,028 lights will be updated.

This project will reduce energy levels, greenhouse gas emissions and will save Council up to $100,000 per annum.

LED Lighting Upgrade

STORMWATER UPGRADE

The Civil Works team took a proactive approach to mitigate a potential flooding issue in March by clearing a blocked stormwater pipe at Freshwater Park. They replaced it with a channel made from recycled sandstone which is now home to a family of ducks.


STRATHFIELD CONNECTOR BUS

In 2023, Council conducted a review and community consultation of the Strathfield Connector bus service. The results indicated that the bus was not an efficient use of Council funds and the following decisions were made:

  • From 2 March 2024 the Bus was reduced to 1 route, servicing the areas identified in the survey as requiring additional transport.
  • The Connector Bus service will cease completely in 2026
  • Council will instead lobby the State Government to cover the public transport black holes in our area.

Read more about the Strathfield Connector Bus consultation here.

Strathfield Connector Bus

UPCOMING PROJECTS

And this is just the start! The below items have also been identified as key projects for the next couple of years:

PROJECTFUNDING
Telopea Ave, Homebush West Bridge$450,000
Playground renewal based on safety audit priorities$200,000
Bates Street Community Centre Renewal Stage 1 (design) $150,000
Road renewal - continuing $1,700,000
Footpath renewal - continuing$4,000,000
TOTAL$6,500,000